Below  is a Preliminary Detailed Bid Tab showing the Apparent Low Bidder and Base Bid Amount indicated.    Indication of Apparent Low Bidder Does NOT constitute the Final Contract Award.  Selection of Contractor for Contract Award subject to Client Consideration / Approval.  This information Does NOT constitute Final Bid Tab, should you require this information, please contact AEI Engineering.
Comments:
* Bidder's written amount differs from numerical amount
 
BIDDER #1
T & C Construction, Ltd              
BIDDER # 2
R J Construction Company, Inc.             
BIDDER # 3
Reddico Construction Company, Inc.             
Item No.  Qty  Unit Description  Unit Cost  Total Price Unit Cost  Total Price Unit Cost  Total Price
1. 1 LS Insurance, Bonds, Permits, and Mobilization, complete as specified for $20,000.00 $20,000.00 $25,000.00 $25,000.00 $38,700.00 $38,700.00
2. 1 LS 8’ x 30’ Precast Lift Station, including reinforcement design, pumps, valves, piping, trough, structure, and all appurtenances, complete as specified and shown on plans for $426,000.00 $426,000.00 $589,710.00 $589,710.00 $718,000.00 $718,000.00
3. 1 EA 8’ x 7’ Junction Box with sealed rim, complete as specified for $15,000.00 $15,000.00 $40,000.00 $40,000.00 $22,800.00 $22,800.00
4. 3 LF 36” Flanged D.I.P. storm sewer force main, including excavation, bedding, and backfill, complete as specified for $1,000.00 $3,000.00 $2,500.00 $7,500.00 $1,900.00 $5,700.00
5. 65 LF 8” Water line, including all fittings, excavation, bedding, and backfill, disinfection, and testing, complete as specified for $100.00 $6,500.00 $100.00 $6,500.00 $87.00 $5,655.00
6. 1 LS Bypass water line, complete as specified for $5,000.00 $5,000.00 $500.00 $500.00 $900.00 $900.00
7. 50 LF Remove and properly dispose of 8” water line, complete as specified for $10.00 $500.00 $85.00 $4,250.00 $12.00 $600.00
8. 37 LF Remove and properly dispose of 36” RCP storm sewer, complete as specified for $300.00 $11,100.00 $70.00 $2,590.00 $24.00 $888.00
9. 1 EA 36” Tide Flex check valve, complete as shown on drawings for $8,000.00 $8,000.00 $11,000.00 $11,000.00 $19,750.00 $19,750.00
10. 71 LF Install and remove temporary 6’ chain link fence, complete as specified for $50.00 $3,550.00 $40.00 $2,840.00 $15.00 $1,065.00
11. 51 LF Install new board fencing to match existing, complete as specified for $50.00 $2,550.00 $60.00 $3,060.00 $68.00 $3,468.00
12. 23 SY Remove and replace sidewalk, complete as specified for $40.00 $920.00 $150.00 $3,450.00 $46.00 $1,058.00
13. 100 LF Trench safety, complete as specified for $10.00 $1,000.00 $5.00 $500.00 $10.00 $1,000.00
14. 1 LS Traffic control, complete as specified and shown on plans for $4,000.00 $4,000.00 $12,000.00 $12,000.00 $7,000.00 $7,000.00
15. 60 SY Sod all disturbed areas, complete as specified for $30.00 $1,800.00 $15.00 $900.00 $6.00 $360.00
16. 2 EA Inlet protection barrier, complete as specified for $200.00 $400.00 $100.00 $200.00 $52.00 $104.00
17. 1 LS Electrical controls and Power drop, including all appurtenances, complete as shown on drawings and per pump manufacturer’s recommendations for $90,000.00 $90,000.00 $30,000.00 $30,000.00 $16,700.00 Text Box: 1
$16,700.00
BASE BID TOTAL   $599,320.00   $740,000.00   $843,748.00
SUPPLEMENTAL ITEMS            
1. 100 LF Trench dewatering, complete as specified for $50.00 $5,000.00 $50.00 $5,000.00 $35.00 $3,500.00
      Comments: 1- Bidder #3, Reddico Construction Company, Inc., submitted an alternate price for Bid Item No. 2. The deduction of $63,748.00 is for a Cast-In-Place method. The Total Base Bid with the alternate price is $780,000.000.